I would say that we're still a week or 2 from being done, but i swung by today (working from the hotel) and they were (surprise!) putting in the granite in the kitchen.
granite closeups:
family room/nook:
laundry: (yes, the machines are ancient - especially the dryer, but they were free and still work)
master bath is still basically gutted. I believe the sink top and plumbing should be ready tomorrow. they're also supposed to build a box for the tub. tile won't be done until the tub is installed.